Blast Furnace Top Gas Recovery Turbine Unit
TRT project of 8# and 7# BF of Xuanhua Iron and Steel Group Co.,ltd
Customer:Xuanhua Iron and Steel Group Co.,ltd
Construction period:2003.12-2004.12
Contract content:BF TRT power generation
With hard working, the TRT power generation project of 8# and 7# BF of the company in form of general contracting realizes successfully startup and incorporation for power generation respectively on December 3, 2004 and December 5, 2004. This is the achievement of all companies involved in the construction including SINOSTEEL MECC which further expands the experiences of SINOSTEEL MECC regarding the BF TRT and it establishes perfect basis for further development of BF TRT project.