Production News

Hot Commissionging Achieved Successfully for 2×240m?Sinter Plant Project for Cangzhou Iron & Steel Complex Phase II

2010-01-28

At 22:38 on December 31, 2009, just before the arrival of 2010, the hot commission of the 2×240m2 sinter plant project of Cangzhou Iron & Steel Complex Phase II, contracted by Sinosteel MECC was successfully achieved in one time, which can be seen as a special welcome to the new year.

At the very beginning of the 2×240m2 sinter plant project of Cangzhou I & S Complex Phase II, the construction was forced to stop for 4 mouths because of the enormous compact and influence of the international financial crisis. With various efforts the project restart in the middle of May,2009. Sinosteel MECC paid high attention on this project to make sure that the project could be successfully put into production in spite of all difficulties, effectively released their producing pressure caused by the shortage of sinter ore.

Presently, Sinosteel MECC’s work team for this project has been working hard to pay the way for allround production of Phase II 200MT Steel-making project.