75 t/h boiler +1*15 MW fuel gas fired power generation project for Pingxiang Iron & Steel Co., Ltd
Customer: Pingxiang Iron & Steel Co., Ltd
Project Time:2010-2011
Contract Type:EPC
Project Schedule:1×75 t/h BFG (mixed with COG) medium temperature medium pressure boiler +1×15 MW condensing steam turbine power generator unit.
In order to fully utilize the excess gas produced during steel making and iron making production process, reduce emission of harmful gas, reduce costs, and realize sustainable development, the project utilizes the excess BFG about 40000 Nm3/h and COG about 10000 Nm3/h of the company to built comprehensive utilization project of gas. The items include: 1*75 t/h BFG (mixed with COG) medium temperature medium pressure boiler +1*15 MW condensing steam turbine power generator unit
This project belong to the scope of energy saving and emission reducing project and it is in accordance with the national industrial policy. After completion of the project, the annual power generation is 1.08×108 kW•h, and the annual power supply is 1.01×108 kW•h.
Construction site for the 75 t/h boiler + 15 MW fuel gas fired power generator.