Coke Oven & By-product Project
2.2MT Coking Project for Cangzhou Zongheng
Customer:Cangzhou Zongheng Industry Company
Construction period: 2008-2010
Contracting scope:
2.2mtpa Coking System: coal blending system, coke screening and stroage system, coke wet quenching system, CDQ residual heat generating system, phyro sewage biochemical disposal station and auxiliary system, etc.
Contracting Type: EPC
Main Technical Characteristics:
To meet the requirements of the 3 sets of 2350m3 BF with production of 5.2mtpa hot metal, this coke oven system includes 4x55 6m compound top-charging coke oven and related coke blending system, coke screen and stroage system, coke wet quenching system, CDQ residual heat generating system, sewage bichemical disposal station and auxiliaries, etc., ensuring annual coke production of 2.2mt, gas purification capacity of 114000m3/h, CDQ capacity of 2x140t/h.
Coking System | By-product Shop Overview |
Typical Projects |
|
2010-09-29
|
|